Lower Pine Creek Road, Chester Springs

43cd4a59_9e8d_45ca_9_IKGwr 47d4ff5a_372a_4c50_b_IYvfS img_1011 img_1023 img_1836 img_1837
43cd4a59_9e8d_45ca_9_IKGwr
47d4ff5a_372a_4c50_b_IYvfS
img_1011
img_1023
img_1836
img_1837

First, we excavated the existing opening to make it larger to accommodate the new entrance. Then, formed and poured the foundation for the new walls. We installed the new cinder block walls and filled them solid with concrete. Then, we installed stucco wire and applied a three coat stucco to the cinder block. Then, we fabricated the new bilco type doors and installed them on the new walls.